A TidalPowerPlant (TPP) is being constructed in the middle section of the existing LakeSihwa dike located near the southern Incheon Port in Korea. The project, which will be completed in 2010, is to harness the largest tidal energy in the Kyeonggi Bay in the eastern Yellow Sea. While noting the current progress in terms of plant construction, this paper outlines the overall project in the tidal
regime and uses predictive local flow modeling. The results of
two-dimensional finite element method simulations that predict the
real-time tidal characteristics during the construction and after the completion of the tidalpowerplant are presented, including a method to estimate the electricity output from the plant in the future.
Keywords
Tidalpowerplant;
SihwaLake;
Tidal modeling
Figures and tables from this article:
Fig. 1. Location of the Lake Sihwa tidal power plant construction site with tidal datum planes.
Fig. 4. Work
procedure of the major construction stage (1) before construction, (2)
silt protection, (3) cofferdam and diversion roads construction, (4)
dewatering, (5) excavation for drywork, (6) Gantry Crane for temporary
wharf*, (7) transport of turbo-generator*, (8)
installation of turbo-generator, (9) construction of road over sluice
gates, (10) detachment of diversion roads, (11) removal of cellular
cofferdam, (12) operational test of turbo-generator. (*This original plan was changed to use special carrier to transport machineries between erection bay and crane sites.)
Fig. 9. Three
types of tidal power generation: (a) single effect operation (ebb), (b)
single effect operation (flood) and (c) double effect operation. Also, a
detailed diagram of a single effect operation (flood) for the Sihwa
TPP.
Fig. 10. FEM
mesh (a) at the cellular cofferdam for Sihwa tidal power generation on
December 2005, (b) on January 2007 and (c) at completed construction.